Chantilly Sewer Design and Survey, Fulton County

Transportation Systems Design, Inc.'s responsibilities for this project included: performing the conceptual and final sewer design engineering, primary control, topographic surveying, coordination with the Fulton County permitting agencies and preparing the Construction Plans for 6,200LF of new gravity sanitary sewer. TSD did some intensive field reconnaissance, which resulted in our firm locating a suitable upstream manhole at which to tie into the system. Because of this work we were able to reduce the need to survey, design and construct a half-mile of new sewer at considerable savings to the County.

Deliverables include: Concept Report, Right-of-Way Plans and Final Construction Plans

copyright (c) 2005 TSD Engineers, Inc.